NASA Kills $2 Billion Mission to Refuel Satellites With Robotic Arm

The Nationwide Aeronautics and Area Administration (NASA) is giving up its mission to refuel previous satellites in orbit, placing an finish to an bold $2 billion mission affected by delays and technical setbacks.

The administration mentioned on Friday that it is discontinuing the hassle after an impartial overview, citing “continued technical, price, and schedule challenges.”

The On-orbit Servicing, Meeting, and Manufacturing 1 mission, or OSAM-1, aimed to construct a robotic arm that might high up satellites that weren’t constructed for refueling, thereby extending their lifespan.

“Want further gasoline or a tune-up in your satellite tv for pc?” pitched its official webpage.

In growth since 2015, it was imagined to launch in 2025, however this was delayed to 2026.

The OSAM-1’s refueling approach appeared nearly like brute drive. A idea video of the robotic arm, known as the Area Infrastructure Dexterous Robotic or SPIDER, exhibits it chopping open a gas hatch, ripping restraints, and unscrewing a gas cap — all whereas in house.

The SPIDER's concept video shows it cutting away a fuel hatch and unscrewing a fuel cap.

The SPIDER’s idea video exhibits it chopping away a gas hatch and unscrewing a gas cap.

NASA



The first goal was to refuel the Landsat 7, a US satellite tv for pc launched in 1999 that wasn’t constructed to be refueled in orbit. The SPIDER may be used to arrange an antenna as a secondary operate.

However the house business as a complete has been pivoting towards satellites already constructed with refueling capabilities, casting off the necessity for such a tool, NASA mentioned.

With fears the mission would possibly grow to be out of date, the administration mentioned it was met with the “lack of a dedicated companion.”

One of many contractors that labored with NASA on the mission was California-based Maxar Applied sciences, which was to supply the spacecraft and robotic arm below contracts value $316 million.

Nevertheless, an audit report in October 2023 slammed the contractor, saying its “poor efficiency” meant NASA had to supply unplanned manpower and engineering assist to assist it ship.

Staff assess parts of a test for the OSAM-1 project.

Employees assess elements of a check for the OSAM-1 mission.

NASA



The spacecraft was delivered to NASA in September 2023, about two years late. In the meantime, Maxar additionally struggled to maintain up with deadlines for the SPIDER, and instructed NASA that it was now not taking advantage of their contract work, the audit report mentioned.

Maxar had “considerably underestimated the scope and complexity of the work, lacked full understanding of NASA technical necessities, and have been poor in vital experience” to fulfill NASA’s requirements, the report mentioned, including that the contractor admitted this as effectively.

The report mentioned Maxar’s delays stemmed from “poor prioritization and staffing,” and that the contractor didn’t run required assessments forward of supply.

The mission’s complete price, which was as soon as estimated to be round $753 million, burgeoned to $2.05 billion by 2022 and was anticipated to additional exceed this funds, the report mentioned.

NASA mentioned it is engaged on mitigating the impression of the OSAM-1’s cancellation on employees on the Goddard Area Flight Heart in Greenbelt, Maryland.

The company instructed CNBC that it had 450 employees and contractors engaged on OSAM-1, and plans on “supporting mission workforce per plan via fiscal 12 months 2024.”

NASA and Maxar didn’t instantly reply to requests for remark despatched outdoors common enterprise hours by Enterprise Insider.